Training Plan

Future Capacity Building Plan for the rest of the Project Period

SL NoActivitiesTimelineResponsibilitiesSteps to be taken for ImplementationRemarks
1Training MIS for UP SecretariesJuly – August 2020PMU, LGSP-3Through MIS FIrm & MIS Unit, LGSP-3 
2Orientation of LGD, NILG & LGHLJuly -August 2020PMU. LGSP-3Preparation of Training Materials by PMU, LGSP-3Programme Design by PMU, LGSP-3Organising Training Programe by PMU, LGSP-3  Subject to the revision of DPP
3Two-day Training for DLGs & DDLGsSeptember 2020PMU, LGSP-3Preparation of Training Materials by PMU, LGSP-3Programme Design by PMU, LGSP-3Organising Training Programe by PMU, LGSP-3  Subject to the revision of DPP
4Three –day Training of DFs including SafeguardSeptember  2020PMU, LGSP-3Preparation of Training Materials by PMU, LGSP-3Programme Design by PMU, LGSP-3Organising Training Programe by PMU, LGSP-3   
5Two-day Training for  DLGs &  DDLGsJanuary 2021PMU, LGSP-3Preparation of Training Materials by PMU, LGSP-3Programme Design by PMU, LGSP-3Organising Training Programe by PMU, LGSP-3  Subject to the revision of DPP
6Good Practice CompendiumDecember 2020PMU, LGSP-3Collection of facts through DFs and preparing the draft in consultation with PMU Consultants Sharing the draft with World Bank and finalisation 
7IEC Service (Production and airing of TV spots, Radio advertisements, Talk shows, documentary film etc)July 2020-August 2021PMU, LGSP-3Hiring of a Media Firm through Open Tender MethodSubject to the hiring of a Media  Firm
8Production of Video TutorialsJuly- December  2020PMU, LGSP-3Hiring of a Communication Firm through Open Tender Method 
9Training of UP Functionaries  using Video TutorialsJanuary 2021-December 2021PMU, LGSP-3 & A2iThrough Union Digital Centres (UDCs) 
10Orientation of Ward Committees & Scheme Supervision Committees using Video TutorialsJanuary 2021-December 2021PMU, LGSP-3 & A2iThrough Union Digital Centres (UDCs)Subject to production of Video Tutorials through hiring of a Media Firm
11Study Tour for 07 Teams each comprising 10 MembersOctober 2020 –June 2021PMU, LGSP-3 & Tour OperatorDevelopment of TOR for selection of Tour OperatorAppointment of Tour OperatorArrangement of TourSubject to the appointment of Tour Operator & concurrence of the World Bank