Future Capacity Building Plan for the rest of the Project Period
SL No |
Activities |
Timeline |
Responsibilities |
Steps to be taken for Implementation |
Remarks |
1 |
Training MIS for UP Secretaries, Entrepreneurs & Accountant-Cum-Computer Operators |
August-September 2021 |
PMU, LGSP-3 & District Administration |
Main Training for MIS System for all Union Parishad (UP) Secretary, Entrepreneur, Accountant-cum- Computer Operator as participant through District Administration of the Concerned District & MIS Team of PMU, LGSP-3 |
Subject to Revision of DPP |
2 |
Good Practice Compendium |
September 2021 |
PMU, LGSP-3 |
· Collection of facts through DFs and preparing the draft in consultation with PMU Consultants · Sharing the draft with World Bank and finalization |
Through Employment of a Firm |
3 |
IEC Service (Production and airing of TV spots, Radio advertisements, Talk shows, documentary film etc) |
July 2021- June 2022 |
PMU, LGSP-3 |
Hiring of a Media Firm through Open Tender Method |
Subject to Revision of DPP and hiring of a Media Firm |
4 |
Training on Union Parishad Development Assistance Guideline (UPDAG) for officials of Field Administration, DFs & selective UP Functionaries (UP Chairmen & Secretaries) |
August- October 2021 |
PMU & District Administration |
· Finalization of Guidelines · Preparation Handouts on Related Topics based on UPDAG |
Subject to Revision of DPP |
5 |
Study Tour for 07 Teams each comprising 10 Members |
August 2021 –February 2022 |
PMU, LGSP-3 & Tour Operator |
· Development of TOR for selection of Tour Operator · Appointment of Tour Operator · Arrangement of Tour |
Subject to DDPP Revision and appointment of Tour Operator & concurrence of the World Bank |